our commitment to enhance and contribute to the development of Singapore’s built environment.
Discover our Projects
Over the years, we have gained expertise and extensive experience in various fields of civil engineering. Our dedication has enabled us to build robust and trustworthy relationships with both clients and partners.

Tampines North EC
Residential
Tampines North EC
| LOCATION: | Tampines Street 62 |
| TYPE: | Residential |
| CLIENT: | TQS Development Pte. Ltd. |
| CONTRACT VALUE: | $185.7 Mil |
| COMPLETION DATE: | Ongoing |
About The Project


HTL Factory
Industrial
New HTL Factory
| LOCATION: | Gul Circle, Singapore |
| TYPE: | Building (Industrial) |
| CLIENT: | Hwa Tat Lee Manufacturing Pte Ltd |
| CONTRACT VALUE: | S$ 25.80 Million |
| COMPLETION DATE: | Apr 2028 |
About The Project
Hwa Tat Lee (HTL) Factory is a two-storey industrial building and one-storey basement project as an extension to the existing Design Development Centre & Ancillaries located at Gul Circle.

Cyberhub
Industrial
Cyberhub
| LOCATION: | Bendemeer Road, Singapore |
| TYPE: | Building (Industrial) |
| CLIENT: | Cyberhub Holdings Pte Ltd |
| CONTRACT VALUE: | S$21.60 Million |
| COMPLETION DATE: | Dec 2026 |
About The Project
Cyberhub is a seven-storey industrial building with basement carpark situated along Bendemeer Road. It was constructed for warehouse and office usage. The project was awarded the Certificate of Merit for Safety Performance Award, and attained a high CONQUAS score of 75.6 points.
Port Maintenance Dredging
Civil Engineering
Port Maintenance Dredging
| LOCATION: | Pasir Panjang Terminal, Singapore |
| TYPE: | Civil Engineering |
| CLIENT: | PSA Corporation Pte Ltd |
| CONTRACT VALUE: | S$4.66 Million |
| COMPLETION DATE: | Jan 2027 |
About The Project
Unlike conventional dredging operations, maintenance dredging is highly challenging due to the stringent requirement in dredging design depths. Having an allowable tolerance of only fractions of a metre, such operations by massive vessels are required to be carried out with immense care to avoid any over-dredging. The fact that it is carried out in one of the world’s busiest ports heightened the difficulty level of project planning and execution. Maintenance dredging was carried out in an area of 280ha in Pasir Panjang Terminal within 9.5 months. State-of-the-art hydrographic survey equipment was adopted to address the strict hydrographic survey requirements set out by the client. Enhancement to our vessels’ depth sensory equipment enabled our team to perform maintenance dredging within the terminal up to the required accuracy. This allowed an economical and efficient dredging and dumping operation to be carried out, delivering the project within budget and on time.

Ayer Chawan Basin
Civil Engineering, Marine & Coastal
Marina East Staging Ground
| LOCATION: | Marina East Drive, Singapore |
| TYPE: | Civil Engineering, Marine & Coastal |
| CLIENT: | Land Transport Authority |
| CONTRACT VALUE: | S $99.30 Million |
| COMPLETION DATE: | Sep 2027 |
About The Project
Marina East Staging Ground (MESG) is a support facility for Land Transport Authority (LTA) projects all around Singapore to deliver excavated materials to the staging ground to be used as infill materials for land reclamation. This helps to reduce the dependency of sand required for conventional infilling works. Materials are weighed, discharged directly into barges and then sent to their designated dumping sites. The LTA projects include but not limited to, MRT Tunnelling, Stations, Flyover and Depots. The team’s display of innovation throughout the project has contributed significantly to the success of MESG. Besides being the first in Singapore to introduce the direct discharged platform at the staging ground, MESG is also the only project then in Singapore approved to use Recycle Construction Concrete with Bricks (RCCB) – green material – as a fill material for the construction of T-bund.

Marina East Staging Ground
Civil Engineering, Marine & Coastal
Marina East Staging Ground
| LOCATION: | Marina East Drive, Singapore |
| TYPE: | Civil Engineering, Marine & Coastal |
| CLIENT: | Land Transport Authority |
| CONTRACT VALUE: | S $99.30 Million |
| COMPLETION DATE: | Sep 2027 |
About The Project
Marina East Staging Ground (MESG) is a support facility for Land Transport Authority (LTA) projects all around Singapore to deliver excavated materials to the staging ground to be used as infill materials for land reclamation. This helps to reduce the dependency of sand required for conventional infilling works. Materials are weighed, discharged directly into barges and then sent to their designated dumping sites. The LTA projects include but not limited to, MRT Tunnelling, Stations, Flyover and Depots. The team’s display of innovation throughout the project has contributed significantly to the success of MESG. Besides being the first in Singapore to introduce the direct discharged platform at the staging ground, MESG is also the only project then in Singapore approved to use Recycle Construction Concrete with Bricks (RCCB) – green material – as a fill material for the construction of T-bund.